Hold points, witness points and why your ITP matters

If you’ve worked on an oil & gas or major infrastructure job, you’ve seen an inspection and test plan – the ITP. It’s usually a long table with columns of letters: H, W, R, S, M. Fabricators sometimes treat it as paperwork for the client. It’s actually the most useful document on the job for avoiding arguments at handover.

What an ITP does

The ITP lists every inspection and test activity in the order the work happens: material receipt, cutting, fit-up, welding, NDT, dimensional checks, pressure testing, coating, final inspection and documentation. For each one it names the procedure or standard, the acceptance criteria, the record that will be produced, and who has to be involved.

That last column is where the letters come in.

Hold point (H)

Work stops until the named party has inspected and released it. If the client’s inspector has a hold point on fit-up of a pressure-retaining weld, the welder doesn’t strike an arc until that inspector has seen the joint and signed off. Skipping a hold point is one of the quickest ways to get work rejected, regardless of how good it is.

Witness point (W)

The named party must be notified and given the chance to attend. If they don’t turn up after proper notice, work can continue. The notice period – often 24 or 48 hours – is written into the contract, so keep a record of when notifications were sent.

Review (R), surveillance (S) and monitor (M)

Review means the party checks the records rather than attending. Surveillance or monitoring means they may drop in at any time without stopping the work. Exact definitions vary between companies, so read the legend on each ITP.

Where ITPs go wrong

  • Too generic. A template copied from another job lists tests that don’t apply and misses ones that do.
  • No acceptance criteria. “Visual inspection” without a code reference means everyone has a different idea of acceptable.
  • Notifications not tracked. When a witness point is missed, nobody can prove the notice was sent.
  • Records left to the end. Trying to assemble a dossier from memory after the job is finished almost always leaves gaps.